Reinforced Concrete Frames
A new Reinforced Concrete Frame project in Croydon
Working for Carty Forde, we were tasked with pumping concrete over a period of 4 months into a basement ready for a new RC frame.
Pouring between 30 โ 770m3 per day, this project often required 2 pumps to work in unison to get the pours completed by 5pm each day.