Suffolk Reservoir
Supporting Bell Formwork on Anglian Water’s Suffolk Reservoir
From March 2024 through to May 2025, Ramcrete supported Bell Formwork in the construction of a new water tank for Anglian Water in Suffolk. Over the course of the project, our pumps played an important role in delivering consistent, efficient pours to keep the build moving.
In total, 2,884.5 m³ of concrete was placed across multiple pours. We supplied a range of mobile boom pumps, from our compact 24 metre boom for tighter areas to our 60 metre boom for long-reach sections, ensuring every stage of the project was completed safely and on schedule.
This project showcases our growing experience in the reservoir sector – a field we’re seeing expand rapidly across the UK. With several reservoir builds completed in 2025 alone, Ramcrete is well-positioned to support the increasing demand for reliable concrete pumping on large-scale water infrastructure.