360m3 poured over a live railway!

When BAM Nuttall took on the replacement of Agar Road overbridge in Camden, they needed a concrete pumping partner who could handle both scale and complexity. Ramcrete supplied two 52 metre boom pumps and delivered an impressive 360m³ in just 7 hours – all over a live railway. With our skilled operators and meticulous planning, the pour was completed safely and on time.

Enquire Now

Project requirements:

  • 2 × 52 metre boom pumps
  • 360m³ poured in 7 hours
  • Careful planning to ensure safety and precision
  • Collaboration with BAM Nuttall from early project stages

Having used Ramcrete on a recent project, we approached Ramcrete early on regarding a major pour for the Agar Grove project since November 2024 and Bradley came along to offer Ramcrete capabilities to support the team. Good planning with Ramcrete team ensured successful pour of around 360m3 for a bridge deck over live railway using 2nos M52 concrete pump in 7hrs.